Prepare for Installation Before you install the Cisco NCS 540, you must prepare your site for the installation. Preparing your site involves these tasks: • General Precautions, on page 1 • Site Planning Checklist, on page 2 • Environmental Requirements, on page 2 •...
We recommend that you install the unit in a fully sealed enclosure or cabinet. Examples of such cabinets include IP65 cabinets with heat exchanger complying with Telcordia GR487. Temperature must be maintained within –40ºC to 65ºC. This is applicable to Cisco N540X-6Z18G-SYS-A/D, N540X-8Z16G-SYS-A/D, and N540X-4Z14G2Q-A/D router variants.
Page 3
Prepare for Installation Airflow Guidelines • Side clearance—3 inches (7.62 centimeters) Figure 1: Airflow Top View Clearance Prepare for Installation...
Page 4
Prepare for Installation Airflow Guidelines Figure 2: Airflow Side View Clearance Prepare for Installation...
Page 5
Prepare for Installation Airflow Guidelines Figure 3: Airflow Side View from Right to Left Figure 4: Airflow Side View of Cisco N540-6Z18G-SYS-A/D Router from Front to Left Prepare for Installation...
Prepare for Installation Site Power Guidelines Table 1: Airflow Guidelines Router Flow Air Clearance Direction N540X-6Z18G-SYS-A Right to Left At least 3 inches (76.2 millimeters) required on both inlet and exit directions. N540X-6Z18G-SYS-D N540X-8Z16G-SYS-A Right to Left At least 3 inches (76.2 millimeters) required on both inlet and exit directions.
The router requires external surge protection devices for installations where electrical surges higher than 4KV common mode and 2KV differential mode are expected. Failure to do so can result in permanent damage to the router. For Cisco N540-6Z18G-SYS-A/D router, 2KV common mode and 1KV differential modes are supported.
Before you install the router, have all the additional external equipment and cables on hand. For information about ordering, contact a Cisco customer service representative. The extent of your network and the distances between the network interface connections depend, in part, on the following factors: •...
Prepare for Installation Prepare Your Location Prepare Your Location This section illustrates how the building that houses the chassis must be properly grounded to the earth ground. Figure 5: Building with Rack Room Connected to Earth Ground Prepare Yourself This section illustrates how to prepare yourself before removing the chassis from the sealed antistatic bag. The figures show how to wear the ESD strap around the wrist and how to connect the other end of the strap to the ground.
Prepare for Installation Prepare Rack for Router Installation Figure 6: Wearing the ESD Strap Prepare Rack for Router Installation Install the chassis into a two-post standard rack with standard horizontal mounting rails. Before you mount the chassis into the rack, we recommend that you do the following: Step 1 Place the rack where you plan to install the chassis.
Prepare for Installation Unpack the Cisco NCS 540 Small Density Router Note Ventilated cabinets and racks are not recommended for OSP applications. Table 2: Cabinet Type for Indoor and Outdoor Installation Cabinet Type Suitable for Indoor Installation? Suitable for Outdoor Installation?
Page 12
Prepare for Installation Unpack the Cisco NCS 540 Small Density Router Be sure to save the packaging in case you need to return any of the components products. Note These images are for only representation purposes. The chassis' actual appearance and size would vary.
Page 13
(Only applicable to Cisco N540-6Z18G-SYS-A/D router) Cable bracket N540-CBL-BRKT-FN Note Most Cisco documentation is available online. The chassis Pointer Card that is shipped with your Cisco NCS 500 Series Services Routers contains links and information to other online documentation. Note If the product is not in use, store the device in the initial packaged condition or in an ESD PE sealed bag with silica gel.
Page 14
Prepare for Installation Unpack the Cisco NCS 540 Small Density Router Prepare for Installation...